Inside the garge before installing a new sewer line.

The driveway area before sewer repair. The white paint is the PA One Call
location of
the main connection of the house to the main sewer. The
manhole on the main sewer is visible next to the bush.

The existing house trap was 8ft. deep. The vent is the small round pipe
full of holes on top.

The garage floor is opened and the new seamless 4" sewer line is ready
to be pulled into the existing pipe. The new pipe is HDPE pipe (High
Density Polyethylene Pipe), which is a superb pipe and somewhat flexible.

The new sewer pipe (black pipe) is about 1/2 way to the street.

The steel cone which is about 6" in diameter has the new 4" sewer line
inside and is entering into the pulling machine at the street.

A new wye connection is installed in the main sewer, as the old one was broken.

The new HDPE sewer pipe is connected to the new wye in the public main
by SDR35 plastic pie. There will be a clean out and site tee which will
extend to the surface from the tee. This is visible in the upper middle of this photo.

A new 4" PVC house trap and cleanout is installed inside the garage area.
This is connected to the existing house sewer on the left and the new
HDPE sewer line on the right.

The finished driveway area with the new cleanout cap visible in the
center of the picture.

The finished garge area with the cleanout & house trap caps and a new
4" vent from the house trap to the outside.